Watch: New Civil Engineer News Wrap on Edinburgh Trams to Newhaven project
Sacyr Farrans Neopul (SFN), in partnership with our client The City of Edinburgh Council and Turner & Townsend, were pleased to welcome New Civil Engineer to our Edinburgh Trams York Place to Newhaven project.
The final sections of Trams to Newhaven track have been laid as the project prepares for the electrification of the full line.
Energisation of newly installed overhead lines during the coming months will allow a testing and commissioning period to begin at the start of 2023.
To date, 4.5km (96%) of track has been laid, with tram track now running continuously from Picardy Place to Tower Place, 100% of utility diversions have been completed and major civil works are finished on five of the eight new tram stops.